| |
FORD ISLAND WATERLINE REPLACEMENT
< Go to page 2
SOCIAL, ECONOMIC AND SUSTAINABLE DESIGN CONSIDERATIONS
Among the primary considerations for the project was the need to improve the
efficiency and reliability of the Navyfs Pearl Harbor water system. This project
provided much needed carrying capacity as well as backup capability for the water
system to maintain water service to all base activities. As a result of the new line,
and with improvements to the overall system, the pumps driving the water system
have been operating more efficiently due to the reduced system gback pressureh.
The lower system operating pressure has basically resulted in lower energy
consumption and greater delivery capability. NAVFAC, Hawaii estimates of energy
cost savings attributed to the system improvements are currently about $50,000
per year.
The application of gtrenchlessh construction methods used in this project also
resulted in minimal impact on the environment. Of specific concern was the
underwater crossing work that may have caused significant disturbance to the
sediments on the Harbor bottom. It was imperative that the Harbor waters not be
clouded with suspended sediment that may contain hazardous or toxic materials.
The pipeline materials used in the project were selected for their corrosion
resistant properties, with the intent of providing maximum service life.
Furthermore, serviceable items such as valves and expansion couplings are
installed in concrete vaults that allow service and replacement without the need to
excavate large areas, reducing future impacts on the surrounding areas.
COMPLEXITY
Various design elements were considered as part of the modified HDD method,
including vertical alignment for minimum pipe bend radius, pulling loads on the
HDPE pipe string, hydraulic design to avoid a mid-length high point, and
permanent harbor bottom ballast to maintain the long term stability of the
installed pipeline.
Containment of HDD drill fluids at the mid-harbor exit locations required adopting
special provisions to prevent contamination of the harbor waters.
Borehole stability, and heave and hydro-fracture potential were assessed for
various drilling fluid scenarios. Risk of consequential damage to the adjacent pilesupported
Admiral Clarey Bridge from potential hydro-fracture or borehole
collapse was also evaluated using finite element analysis of combined pipe and
bridge soil-structure interaction, confirming HDD to be the preferred solution as
compared to underwater gcut and coverh (trenching) methods. Construction
observations were also vital for project success, including offshore Tru-Tracker.
drill head navigation to insure proper bore hole alignment, avoiding
encroachment into the bridge foundation support zone and eliminating high
points in the smooth sweeping pipeline profile. Constant monitoring of pull loads
was also required to avoid overstressing the pipe string, which could potentially
permanently impair the pressure rating and longevity of the waterline.
Surface barge staging operations, with an assist rig to provide support of the
pipeline during the over water staging and pipe string insertion operations, were
required. Also, dive operations for the final underwater splice connection were
also required to complete the installation of the submarine line.
MEETING AND EXCEEDING THE CLIENTS EXPECTATIONS
FAINC and the design team were fully engaged in support of the project from
inception, through development, and final completion, partnering with both the
client (NAVFAC Pacific) and the owner (NAVFAC, Hawaii), as formalized in the
FACD effort. As with most projects the construction cost was a major concern. It
was a significant challenge to meet project objectives within the available budget.
For this project, the original programming documents had set the estimated
construction cost (ECC) at $12.6 million. The final design construction cost
estimate was $12.1 million, and the actual final construction cost was $12.0
million. Much of the cost savings can be attributed to the innovative design of the
under channel pipeline crossing.
The greatest long-term benefits to the Navy will be from more energy efficient
operations and enhanced system reliability. The new water system installed on
Ford Island will support proposed developments that will transform the island into
a vibrant commercial, visitor and operations center within Pearl Harbor.
The design team completed the project on time and within the design budget,
earning a Certificate of Appreciation from the Navy for "outstanding design and
engineering services, responsiveness and highest level of professionalism." The
project was put out to bid on schedule in 2002, with construction commencing,
also as scheduled, in 2003. The project was substantially completed in 2005.
The waterline was operational and ready to support several key Ford Island
facilities including the National Oceanic & Atmospheric Administration Pacific
Regional Center and Ship Operations Facility (under construction), the Pacific
Warfighting Center (in design), and the Pacific Aviation Museum (under
construction).
Go back to page 1 >
|
|